Genset voltage unbalance is the gap between the three line voltages, and a motor heats on it faster than the percentage suggests. Read the phase record and the negative sequence limit, then compare the derate against the panel before you accept a rating. Tesla Power quotes both; send the record to the document desk for a quote. The page separates the three line voltages and shows what their spread does downstream. A motor reads an imbalance as a backward-turning component, so the heating that follows is larger than the percentage suggests, and the page explains why that ratio is what limits the set. Ask for the negative sequence limit, not a general tolerance. The two are not the same figure. It then covers how the figure is measured, how single-phase loads are moved to correct it, and what an offer has to state before a panel is ordered against it.
- Ask for the phase currents rather than one total, because the heaviest phase decides the rating.
- Check the negative sequence limit, since it is a separate limit from the kW figure.
- Look at where the record was taken, because the panel and the terminals give different numbers.
- Ask how the single-phase load is spread, since the spread is what creates the unbalance.
What does genset voltage unbalance measure?
It measures how far the three line voltages differ from each other, expressed as the largest deviation from the average as a percentage of that average. A set with phases at 400 V, 400 V and 380 V shows a deviation of 20 V, so 20 V / 400 V = 5% unbalance on the definition a motor maker uses. The figure sounds small and the effect on a motor is not small at all.
The unbalance comes from single-phase loads spread unevenly, from a broken or high-resistance connection, or from a set whose windings were not matched. A genset for a motor bank carries the first cause most often, because a workshop adds a welder on one phase and a lighting circuit on another. Tesla Power asks for the phase currents at the panel before quoting, and for the hour they were taken, since a welder on shift changes the picture between one reading and the next.

Why does a motor heat so fast on an unbalanced supply?
An induction motor reads an unbalanced supply as two components, a positive sequence that turns forward and a negative sequence that turns backward. The backward component produces a braking torque and a rotor current at twice the supply frequency, and that current flows in the rotor bars and the end rings, where the heat has nowhere to go and no fan to carry it away. A motor on a soft supply often fails at the rotor before the stator shows anything on a clamp.
The effect is far larger than the voltage figure suggests, because the negative sequence impedance of a motor is close to its locked rotor impedance. A 2% voltage unbalance produces a current unbalance of perhaps 12%, and the temperature rise follows the square of that current. Tesla Power Equipment states the negative sequence limit on the alternator sheet for exactly this reason.
| Voltage unbalance | Motor current unbalance | What it does |
|---|---|---|
| 1% | about 6% | Warm, inside the rating |
| 2% | about 12% | The derate begins |
| 3% | about 18% | The winding runs hot |
| 5% | about 30% | Derate to 75% or stop |
| Balanced | under 2% | The figure to design for |
How is the figure measured?
A meter that reads the three line voltages at the same instant gives the figure directly, and a clamp on each phase gives the currents that matter more. A reading taken phase by phase with a single instrument is not a simultaneous reading, because the load moves between the three measurements and the record then describes three different hours, and the average of them is a figure that no instrument ever measured.
Take the record at the panel that feeds the motors rather than at the set terminals, because the cable and the board sit between them. A genset for the site has to be read at the point where the load is connected, and the difference between the two points is often the whole of the problem. The 500kVA silent set with ATS changeover is quoted with the phase current it can hold at each terminal, and Tesla Power asks which of the two points the buyer used for the load study.

What does the alternator do about it?
The alternator produces what the load draws, and an unbalanced load produces an unbalanced current in the stator. That current sets up a field that turns against the rotor, and the damper winding carries the resulting current as heat. The alternator therefore has a negative sequence limit of its own, separate from its kW rating and separate from its kVA rating, and the two limits are printed on different lines for that reason.
A set rated at 400kVA at 0.8 pf gives 320kW on a balanced load, and the same set carries less when one phase is loaded to its limit and the others are not. Ask for the negative sequence limit on the alternator sheet. The 1000kW hospital container is quoted with that limit stated, because a set bought on kW alone has no line to check it against, and the gap shows up as a hot phase rather than as a trip.
What does a high figure do to the set?
The winding that carries the heaviest phase reaches its temperature first, and the set is then limited by that winding rather than by the total. A set with a 5% unbalance may be unable to deliver its rating at all, because one phase is already at its limit while the other two still have headroom on the meter. The set is not overloaded on paper and it is overloaded in one winding.
The derate is stated against the unbalance rather than against the load, so the two figures have to be read together. Ask for the derate table rather than a single number. The rating based set list sets out the phase balance test we run, and Tesla Power issues the derate against the record taken on site rather than against a nameplate figure.

How is the load balanced?
Move the single-phase loads until the three phase currents sit within a few percent of each other, and measure again after the move rather than before it. A workshop that adds a circuit each year drifts out of balance without anyone noticing, and the drift stays invisible until a motor fails in the busy season, which is the week the plant cannot afford a stop.
A genset in a workshop with a mixed load needs the board laid out for balance from the start, with the single-phase circuits spread across the phases and labelled. A board wired for a balanced load and added to for ten years is a board that needs an audit. The ISO 8528-1 rating summary gives the limits a supply has to meet at the point of connection.
What does the offer need to state?
An offer has to state the unbalance the set will accept, the negative sequence limit of the alternator and the derate that follows from it. Three lines let a buyer check the offer against the panel record. A figure quoted as a percentage without the limit behind it cannot be checked, and most genset manufacturers leave the limit off the sheet entirely, which leaves the buyer with a percentage and nothing to compare it to.
The phase currents of the site belong on the same sheet, because they are the numbers the site can measure before the set arrives. Genset suppliers in China often quote a limit from a standard without saying whether it applies to the set or to the installation. A genset factory in China that prints both is easier to compare, and Tesla Power prints both.
What does the handover file record?
The file carries the phase currents at commissioning, the unbalance they give and the derate that was applied. A buyer who reads the file can see whether the set was commissioned on the real board or on a test bank with three equal resistors, and a bank hides every unbalance the site has. A commissioning record taken on a bank is a record of the alternator, and the site is what the buyer is paying for. Ask for the board record as well, taken with the real single-phase load connected and the welder on shift.
The genset quality records for an unbalance check also carry the winding resistance of each phase, because a set with one high resistance joint shows the same symptom as an unbalanced load. Yangzhou Tesla Power issues the resistance record with the test log, the NFPA 110 service table gives the standard the check follows, and the Jiangsu works and test bay shows the bay where it was taken.

Frequently asked questions about genset voltage unbalance
A limit of 1% is the usual figure for a motor on a long duty, and 2% is the figure at which most makers begin to derate. Above 5% the motor is running on borrowed life. The percentage is small and the current it produces is not, so the limit is worth reading twice.
It is heated by it, because the negative sequence current flows in the damper winding and the rotor. A short excursion is absorbed and a standing unbalance is not. Ask for the negative sequence limit and treat it as a limit on the load rather than on the set.
It cannot. A regulator holds the average voltage and it has no way to correct one phase against another. A set with a standing unbalance keeps it whatever the regulator does, so the answer is at the distribution board rather than at the set.
A single-phase welder draws its current from one line pair, and the other phases carry less while it works. A workshop with two welders on the same pair and none on the third has a standing unbalance that follows the shift pattern. Spread the single-phase circuits and the figure falls.
A larger alternator has a lower impedance and produces a smaller voltage deviation for the same unbalanced current, so it helps the motor. It costs more and it runs at a lighter load. Compare the larger frame against a rebalanced board on the annual fuel bill.
It is applied to the rating the set would carry on a balanced load, and it is stated against a measured unbalance rather than a guessed one. Tesla Power issues the derate table with the alternator sheet, so the figure can be checked against the panel record at commissioning.